Problem When we change the Remaining duration of an activity, it keeps reverting to the original value. Change the Remaining Duration value of an activity Reason & Solution There could be two reasons of this problem: 1. There is an "Expected Finish" constraint on the activity. When using an Expected Finish constraint, the remaining duration... Continue Reading →
Primavera P6 XER Import is slow / hanged when importing Risk Category and How to avoid this
When importing an Primavera P6 XER file, P6 Professional could be very slow or hanged when it starts to import Risk Category like the picture below. Primavera P6 Import with Risk Category These Risk Category comes from a Primavera model or database that use Risk Analysis application. If we do not use this Risk Analysis... Continue Reading →
Primavera P6 Constraint: How does it work?
1. Purpose of Constraints in Primavera P6 Date restrictions used to reflect project requirements that cannot be built into the network logic.More accurately reflect real-world aspects of a project.Provide added control of a project.Apply to the entire project or to individual activities.Commonly used project-level constraint: Must Finish ByCommonly used activity-level constraint: Start On or AfterNo... Continue Reading →
Typical Delay Analysis Methods in Construction Claims
This article addresses the concepts of several typical delay analysis methods in construction claims. Why do we need Delay Analysis in Construction Claims? Because The Delay Must Affect The Critical Path The Construction Contracts often state that no adjustment to the critical milestones dates or the scheduled completion dates would be made unless the delay... Continue Reading →
How does Primavera P6 determine a driving relationship between activities?
The Driving Relationship is determined based on the Relationship Free Float and the business rules for Driving Relationships. Relationship Free Float Relationship Free Float (Rel FF): The Free Float on the relationship. Calculated as Successor Early Start (assuming a Finish to Start relationship) - Relationship Early Finish on the predecessors' calendar. This field is computed... Continue Reading →
How does Primavera P6 determine or identify the longest path?
In Primavera P6, when we use "longest path" option to determine the critical path, the process to determine the longest path is as follows: The longest path activities are determined by reviewing the schedule backwards (starting from the last activity) through the driving relationships; If the relationship between two activities is driving, then both activities... Continue Reading →
How to remove the gap between actual bar and remaining bar in schedule update in Primavera P6
In the schedule update of Primavera P6, there are occasionally gaps (empty spaces) between the actual bars and the remaining bars as illustrated in picture below. The reasons and solutions for the issue are described in this article. Reason 1: Primavera P6 schedules and displays the activities on Gantt chart in a very detailed and... Continue Reading →
Primavera P6: Schedule Options – Calculate start-to-start lag from
In Primavera P6 Schedule Options, there are 2 options for "Calculate start-to-start lag from". The purpose of these option is described below. We have a simple project: Activity A has FS relationship with Activity B Activity B has SS relationship with Activity C with a lag value of 2 days. The schedule option in this... Continue Reading →
Forensic / Delay Schedule Analysis – Summary Graphic Report in 1 Page
After performing delay analysis work in Primavera P6 or MS Project, we should make a summary graphic report for high-level manager. It would be difficult to get the overview of the analysis with a detail report like the following picture: A simple bar chart or timeline would be more effective and I would like to... Continue Reading →
How to perform Collapsed As-Built / As-Built But-For Schedule Delay Analysis in Primavera P6
Introduction An Collapsed As-Built / As-Built But-For Schedule Delay Analysis (ABBF) is a retrospective CPM schedule delay analysis technique that determines the earliest date that the required project completion activity, or various milestone activities could have been achieved but-for the owner-caused delays that occurred during the project. The amount of owner-caused delay determined from the ABBF Schedule... Continue Reading →
How to use an iPad as a second monitor
As a planner, we usually need a second monitor to be more productive. If you have an iPad, you can easily make it a second monitor. Here are the steps: On our iPad, go to App Store and search for "Duet Display". Buy this app (around 20 USD) and install it on our iPad. On... Continue Reading →
How to Install 2 Primavera P6 versions on the same computer
With Primavera P6 version 18, we can easily install the new version 18 and keep the old version (for example version 16) on the same computer. After download version 18 installation source, click on Setup: We will uncheck the option "Replace existing version": Click Install as usual: After finish installation, on the Start menu we... Continue Reading →