Microsoft Project version 2013 or later provide a function named "Task Path" to highlight the driving predecessor or successor in gantt chart but not provide a function to filter the activity. We can create a macro to filter activity based on "Task Path" function. Go to View -> Macros -> Visual Basic Right click on... Continue Reading →
Print report show predecessors in Gantt chart
To show Predecessors of an activity we can use Relationship tab: However it's quite difficult to identify what are those activity. How about we can show them in Gantt chart. That will be more easy to understand. First you choose View -> Collapse All. Go to the activity you want to show Predecessors. Select a... Continue Reading →