Benefit of using Primavera P6 in Delay Analysis

Primavera P6 software can be very useful in delay analysis work. Some of the benefits are described as follows. 1. Filter which activity affect the critical milestones There could be many delay events happened in a project and each delay event affects certain activities. What are the delay events or activities impacting the critical milestones?... Continue Reading →

Impacted As-Planned Delay Analysis : Using Primavera P6 to see combined / consolidated effect from some or all delay events

Suppose that the project have 5 delay events. If we need to see a combined effect of delay event 1 and delay event 2, we have to create a new project and insert those delay events. Then if we need to see a combined effect of delay event 1 and delay event 3, we have... Continue Reading →